Documents Required for Initial Review
Send available documents early so technical issues can be identified before submission.
Project and drawings
- Site location plan
- Architectural / structural / civil drawings
- PUB service plans if available
- Proposed scope of engineering works
- Contractor contact and project schedule
Construction and risk information
- Method statement
- Construction sequence
- Excavation / piling / ERSS details
- Temporary works drawings
- Risk assessment
- Protection measures for sewer or water main
- CCTV report where applicable
- PE / QP endorsement where applicable
Tips for preparing the documents
- Site plan: show the site boundary, the affected sewer, manhole or water main, and dimensioned offsets from the proposed works.
- Sections: show the depth of excavation or foundations relative to the invert or crown level of the pipe.
- Method statement: describe the construction sequence, plant and equipment, temporary works and how the asset will be protected and monitored.
- Temporary works design: where excavation support or piling is near the asset, include the PE-endorsed design.
- Monitoring plan: where required, show instruments, readings frequency and alert levels.
- Contacts: name the responsible QP, contractor and site supervisor.